City Centre Project Update - City Centre redevelopment plans for 2025
April 11, 2025
Following three years of significant construction in the City Centre area, the focus of work for theĀ 2025 construction season will be on watermain and sanitary sewer rehabilitation, as well as surface rehabilitation.
Mohr Avenue watermain and sanitary sewer rehabilitation
Starting April 14 and continuing until the last week of June, the remaining water mainline and sanitary sewer mainline rehabilitation work from 2024 will be conducted along Mohr Avenue, Spruce Glen (East) to Queen Street. Temporary water will be provided to affected residents for the duration of the construction.
Traffic disruptions, including phased road closures, should be expected in the area.